What: Westbound U.S. Route 60 traffic shifted to new lanes at Missouri Route 125 in Rogersville
When: Monday, December 18, until the completion of phase 4
Details: Contractor crews will begin traffic control and moving barricades on Monday, December 18 at 9 a.m. with the traffic shift completed by 7:30 p.m. Crews are in Phase 3 of the U.S. Route 60 and Missouri Route 125 Interchange Project.
Traffic Impacts:
- Westbound U.S. Route 60 traffic shifted to new lanes at Missouri Route 125 in Rogersville
- Route 60 and Route 125 open in both directions
- Signal at Route 60 and Route 125 will allow left turns one direction at a time from the left driving lane
- Both directions of Route 60 are reduced to two 10’ lanes in each direction
- Speed is reduced to 50 mph in the work zone
- Electronic message boards located near the planned road work will alert drivers to any changes in the work schedule
Weather and/or scheduling conflicts could alter the work schedule.
Project information:
- Contractor: Capital Paving & Construction LLC, Jefferson City
- Completion Dates
-
- Outer Road north of Route 60: November 1, 2023 (Completed)
- Route 60/Route 125 Interchange: November 1, 2024
- Total estimated cost: $20.4 million
- Project website: https://www.modot.org/route-60-route-125-interchange
- Sign up for project updates: Route 60/Route 125 Project Sign Up
- View the Route 60/Route 125 Roundtable Discussion Video
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest