Counties Impacted
Boone
Route Impacted
70
Planning Phase

Boone County: Potential Interstate 70 Exit Ramp Removal

Project Details:

When: 

This project could take place when funding becomes available.

Cost: 

The total estimated cost to remove the existing structure and close the off-ramp is $1.2M.

Proposed Work: 

Removal of the Interstate 70 westbound ramp to Business Loop 70, including the bridge (L0928) constructed in 1957 over eastbound I-70 in the City of Columbia between Route B (Paris Road) and the I-70/U.S. Route 63 Connector. 

Traffic Impact:  

The I-70 westbound ramp to I-70 Business Loop will be closed during demolition.  Temporary lane closures will be intermittently needed on I-70 during construction. 

Additional Right of Way:

No Additional Right of Way is expected to be needed for this bridge removal.

Project Milestones

Complete
Public Comment Period
September 13-24, 2021
milestone_icon
Not Started
Bid Awarded

The project is expected to be awarded when funding becomes available. This project is not currently programmed.

milestone_icon

PROJECT NEWS

Image
Social Media Icons

Stay Connected!

Check out facebook.com/modotcentral and @MODOT_Central on Twitter to follow us and know what's happening near you! You can also click the button below to subscribe to district news and have the information sent straight to your inbox! 

Subscribe to Email/Text Updates