Counties Impacted
Montgomery
Route Impacted
19
70
Work Type
Interchange Improvements
Completed

Project Milestones

Complete
Public Meeting to Discuss Project Options
(Feb. 11, 2020)
milestone_icon
milestone_icon
Complete
Re-evaluation of I-70 Study - Environmental Impact Study
(November 2020)
milestone_icon
Complete
Final Design Completed
Falls 2021 - Video Available About Project

Overview of Project   

If assistance is needed for another language or closed captioning, please contact necr@modot.mo.gov.

milestone_icon
Complete
Right of Way Acquisitions
Fall 2021 - Spring 2022
milestone_icon
Complete
Project Bid Opening to Contractors
June 2022
milestone_icon
Complete
Project Awarded
(July 2022)
Contractor: Emery Sapp & Sons, Inc.
Contract Amt: $14.6M
milestone_icon
Complete
Construction
Anticipated to begin late Summer/Fall of 2022
Videos about construction
milestone_icon

News to Know

  • New MO 19 & I-70 Interchange Completed at New Florence

    09/19/2023

    HANNIBAL – Over two months ahead of schedule, the bridge replacement and interchange project located on Missouri Route 19 and Interstate 70 fully opened to traffic today, September 18, upon completion of the north roundabout.

    Contractor crews with...

  • New South Roundabout Opens at New Florence Interchange

    08/31/2023

    HANNIBAL –The bridge replacement and interchange project located on Missouri Route 19 and Interstate 70 is set to enter the final stages including reduced traffic impacts.

    Weather permitting, September 1, the following portions of the project will...

  • Missouri Route 19 Now OPEN at New Florence

    08/11/2023

    HANNIBAL –Missouri Route 19 opened this morning near New Florence after being temporarily closed for construction work to complete the tie-in work at the south roundabout at the new interchange at I-70.

    Stage 4 of construction now begins with...