Joplin Public Library, 1901 E 20th St, Joplin
This is a come-and-go style meeting with no formal presentation. If you cannot attend, please review the project information and complete the comment form below by April 9.
Project Information
- Replace pavement and widen I-44 to 6 lanes between Missouri Route 43 (Main Street) and Loop 49 (Range Line Road)
- Additional lanes will be installed in the median
- The City of Joplin will install a new culvert under I-44 at Silver Creek
- Estimated Total Cost of MoDOT portion of project: $25.1 million
Traffic Impacts
- Narrowed lanes, traffic shifts on I-44
- I-44 will maintain two lanes of traffic in each direction, except for short-duration closures during nighttime hours
- I-44 ramp closures
- During higher traffic volume, drivers can expect delays
NEWS RELEASES
-
TRAFFIC ALERT: New Schedule for Work at Intersection of Route 97 & Route 60 Beginning Week of July 6
Where: U.S. Route 60 between Barry County Farm Road 1020 and Barry County Farm Road 1040 north of Monett Regional Airport
When: Monday, July 6 through Friday, July 31
What: Contractor crews widening the south side of Route 60 for future traffic shift...
-
Watch for Lane Closures, Delays During Guardrail Work on Route 60 in Barry & Newton Counties
Barry & Newton Counties – Drivers should prepare for lane closures and occasional traffic delays on U.S. Route 60 between the Missouri/Oklahoma state line and Missouri Route 37 (Central Avenue) in Monett while a contractor installs guardrail in...
-
Westbound Interstate 44 to Remain CLOSED at Exit 11 for Extended Period
JASPER COUNTY - Due to an incident on the Oklahoma Turnpike, westbound Interstate 44 is CLOSED at mile marker 11 near the Missouri-Oklahoma state line for an extended and unknown duration. The Missouri Department of Transportation recommends all...
-
TRAFFIC ALERT: Off Ramp CLOSED on NB I-49 at Route FF (Exit 39A) in Joplin June 15 & 16
Where: Northbound I-49-to-Jasper County Route FF (Exit 39A) off ramp in Joplin
When: 8 p.m.-5 a.m., Monday & Tuesday, June 15 & 16
What: Contractor crews inspecting truss signs
Traffic Impacts:
- Northbound I-49-to-Jasper County Route FF (32nd Street)...
-
TRAFFIC ALERT: Expect Lane Reductions, Delays on WB I-44 at Exit 1 in Joplin June 15 & 16
Where: Westbound I-44 at U.S. Route 166 (Exit 1) off ramp in Joplin
When: 8 p.m.-5 a.m., Monday & Tuesday, June 15 & 16
What: Contractor crews inspecting truss signs
Traffic Impacts:
- Expect periodic lane reductions and possible traffic delays
- Watch...
Frequently Asked Questions:
Will I-44 be closed?
I-44 will have nighttime lane closings at times, but will have two lanes of I-44 traffic in both directions open during daytime hours.
Why are sound walls not being built?
A noise study is done whenever MoDOT adds through lanes, a new road or changes the alignment of a roadway. We can only build walls in those locations where all criteria are met. Additional information on the noise policy can be found here.
What type of pedestrian improvements will be constructed with this project?
The City of Joplin is constructing a new underpass to allow pedestrians and bicyclists to cross under I-44 at Silver Creek. The new underpass will be built concurrently with the I-44 widening project. Please contact the City of Joplin for additional information on the shared-use path.
Is MODOT purchasing property from landowners?
No right-of-way is anticipated currently.
How can I learn more about the I-44 Design-Build Project?
Information about the upcoming I-44 Design-Build Project can be found at the following link: Forward 44: Southwest I-44 Improvements Project | Missouri Department of Transportation
The last day to leave comments on this project is April 9.
Project Contacts
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info
Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Southwest Missouri Council of Governments: Barry, Christian, Dade, Dallas, Greene, Lawrence, Polk, Stone, Taney, & Webster Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Southwest Missouri Council of Governments: Barry, Christian, Dade, Dallas, Greene, Lawrence, Polk, Stone, Taney, & Webster Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Kristi Bachman
Title
Forward 44 Southwest Project Director
Department
Southwest District
Contact Info
Email: Kristi.Bachman@modot.mo.gov
Phone: (417) 834-7171
Fax: (417) 895-7664
Email: Kristi.Bachman@modot.mo.gov
Phone: (417) 834-7171
Fax: (417) 895-7664