plans Project Summary

The Missouri Route 7 bridge over Interstate 44 was built in 1977. While the supporting structures are in good condition, the driving surface has deteriorated, is in poor condition, and needs replaced. The new bridge deck will have new drains, bridge approaches upgraded, and new, updated guardrail installed. 

Project Progress

Complete
Planning and Design

The Missouri Department of Transportation and its consultant have designed a new deck to extend the functional life of the bridge.

The estimated cost for these improvements, including engineering and construction, is $2.7 million. This cost may change.

milestone_icon
Complete
Public Input
The three-week comment period is open from June 17 through July 8.

A public meeting will be held at Richland City Hall on June 24, 2025, from 4:30 to 6 p.m. There will be no formal presentation, and participants may come and go to submit comments at any time during the meeting. The project team will be on hand to answer questions and discuss the project. 

Additionally, there are three other ways to submit your input on the project:

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

The project was part of MoDOT’s January 2026 letting when contractors were able to submit competitive bids. During its Feb. 4, 2026, meeting, the Missouri Highways and Transportation Commission awarded a $1,911,000 contract to West Plains Bridge & Grading, LLC to complete the bridge replacement project. At that time, the contractor was given a notice to proceed date of March 6, 2026. This is the earliest date the contractor may begin work. 

milestone_icon
In Progress
Project Construction, Traffic Impacts, and Completion
Closed July 13 - Dec. 1, 2026

Route 7 over I-44 closed the morning of July 13 and will remain closed through early December for crews to replace the bridge deck. There is no access across I-44, and motorists must use an alternate route. Those traveling southbound Route 7 or to eastbound I-44 will be directed to use westbound I-44 to Missouri Route 133 (Exit 145) to eastbound 1-44. Those traveling north to Route 7 or to westbound I-44 will be directed to use eastbound I-44 to Missouri Route 17 (Exit 153) to westbound I-44.  

Removal of the existing bridge deck will require I-44 to narrow and the ramps to close – two nights each direction – overnight July 15 - 18 as follows: 

  • July 15 & 16, 7 p.m. – 6 a.m., nightly:  

    • Eastbound I-44 ramps to and from Route 7 will be closed. 

    • Eastbound I-44 reduced to one lane and directed up and over the ramps at Exit 150. 

  • July 17 & 18, 7 p.m. – 6 a.m., nightly:  

    • Westbound I-44 ramps to and from Route 7 will be closed. 

    • Westbound I-44 reduced to one lane and directed up and over the ramps at Exit 150. 

For the remainder of construction, the on- and off-ramps at Exit 150 will remain open. 

milestone_icon

destination Project Location

Google Map
Google Map

news Project News

  • SCHEDULE UPDATE: I-44 to be narrowed, rerouted overnight July 20

    07/17/2026

    JEFFERSON CITY, Mo. – The narrowing of Interstate 44 in Pulaski County, west of Waynesville, has been rescheduled. Instead of narrowing to one lane overnight July 17 and 18, the contractor now plans to remove the bridge deck (driving surface) of the...

  • UPDATE: I-44 to be narrowed, rerouted overnight July 15 - 18

    07/14/2026

    JEFFERSON CITY, Mo. – Interstate 44 west of Waynesville in Pulaski County is set to narrow to one lane overnight this week as the deck (driving surface) of the Missouri Route 7 overpass is removed. 

    Monday morning, July 13, construction crews working...

  • Route 7 over I-44 to close for bridge project in early July

    06/24/2026

    JEFFERSON CITY, Mo. – Missouri Route 7 over Interstate 44, west of Waynesville, is set to close in early July for five months as the bridge’s driving surface is rebuilt. The first step will be removing the existing deck, which will require narrowing...

  • MoDOT seeking public input on Missouri Route 7 bridge project

    06/11/2025

    JEFFERSON CITY, Mo – The Missouri Route 7 bridge over Interstate 44 in Pulaski County, west of Waynesville, needs rehabilitation. Built in 1977, the supporting structures are in good condition, but the bridge’s deck – or driving surface – has...

Frequently Asked Questions

Why is MoDOT replacing the bridge deck?

The Pulaski County Route 7 bridge over Interstate 44 was built in 1977. While the supporting structures are in good condition, the driving surface has deteriorated, is in poor condition, and needs replacement.

For the safety of our construction crews and motorists, the bridge will be closed during construction for up to 145 days, beginning July 6, 2026, and completed by Dec. 1, 2026. Detours will be signed using I-44 Exit 153 and Exit 145. Some nighttime single lane closures will likely be necessary on I-44. 

Closing the bridge gives construction crews space to work, provides added safety for them and the traveling public, and shortens the construction timeframe, reducing the amount of time traffic is impacted.

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Pulaski County Route 7 over I-44 Project on your inquiries.

Sign up for project-specific updates using the form below.

Webform
Sign Up for Project Updates via Email
*
*
How did you hear about this project?
How clearly did the information on the website explain the project?
What is most important to you when considering this project?
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.