Counties Impacted
Callaway
Boone
Route Impacted
70
54
63
Work Type
Corridor Upgrades
In Progress

Project Summary

MoDOT, in coordination with the Federal Highway Administration, is finishing the re-evaluation process to update the Environmental Impact Statement (EIS) of Interstate 70 (I-70) between U.S. 63 and U.S. 54.

As work to update the Environmental Impact Statement wraps up, Improve I-70 Columbia to Kingdom City has transitioned to a Design-Build project. Millstone Weber has been selected at the best-value proposer and Design-Build contractor of Improve I-70: Columbia to Kingdom City. This $405 million fixed-cost contract includes $123 million previously programed for the interchanges at U.S. 63 and U.S. 54.

This project will improve the 20-mile stretch of I-70 between U.S. 63 and U.S. 54 and is one of several projects which will widen the I-70 corridor across the state.  Construction could start as early as Summer 2024 with an anticipated completion date in late 2027.

Since its original construction more than 50 years ago, I-70 has been a vital lifeline for moving people, goods, and information across Missouri and beyond.

Best Value-Proposer Selection

The Missouri Highways and Transportation Commission has selected Millstone Weber as the apparent best-value proposer and design-build contractor of the first project in MoDOT’s Improve I-70 Program. Negotiations to finalize the contract are currently in progress. Construction is scheduled to begin in summer 2024 with an anticipated completion in late 2027.

MoDOT plans to host additional public information meetings in central Missouri in spring 2024 ahead of construction where project plans and traffic control details for project #1 will be shared. 

To learn more about the Design-Build delivery process, click here.

Project Goals

  • Deliver the project by the end of 2027 within the program budget. ​

  • Provide a third lane of travel for eastbound and westbound Interstate 70 from Columbia to Kingdom City.​

  • Improve I-70/U.S. 63 and I-70/U.S. 54 Interchanges providing for better traffic flow and movement of freight. ​

  • Improve the interstate while modernizing the existing pavement and bridges​

  • Minimize construction impacts through communication and construction staging while maintaining safety and mobility. ​

  • Provide expanded employment opportunities to a diverse workforce. ​

Stay Informed: Recent News

Current Construction and Potential Traffic Impacts

 I-70:
  • Barrier wall, narrowed lanes, and a reduced speed limit (55 mph) is currently in place along both directions of I-70 between Callaway County Route J/Millersburg mile marker 137 and Callaway County Route M/Hatton mile marker 144. 
    • Overnight single lane closures should be anticipated in the area.
    • Two lanes of traffic will remain open during peak travel times (7 a.m. to 7 p.m.).
  • The dedicated lane along eastbound I-70 leading to the exit ramp to the U.S. Route 63 connector (mile marker 128) has been shortened. 
    • Motorists may experience delays when trying to merge into this lane.
U.S. Route 63:
  • A crossover is in place along U.S. Route 63 between the Broadway overpass and the Conley Rd. underpass for bridge construction. All traffic is currently shifted to the northbound Route 63 lanes. Traffic is briefly reduced to one lane before entering the crossover where two lanes are open in each direction. 

Current Traffic Impacts

Embed
Improve I-70: Columbia to Kingdom City
Is Responsive
Embed Code
Image
Improve I-70 Project #1 Columbia to Kingdom City Rendering of Three Lanes

Frequently Asked Questions & Project Plans

Have a question? Need to see the plans? Use the links below for more information. Note: Due to file size, some documents may not open correctly on mobile devices. Please open the documents via a desktop computer if files are not opening correctly. You can also e-mail improvei70@modot.mo.gov for assistance. 

What improvements does this project include?

Improve I-70: Columbia to Kingdom City will add a third lane to I-70 in both directions from U.S. Route 63 in Columbia and Route 54 in Kingdom City. Additionally, this project has incorporated two previously funded MoDOT projects to also improve the I-70 interchanges at U.S. Routes 63 and 54. 

What is the project timeline?

Construction began in July 2024. Completion of this project is anticipated to by the end of 2027.

Construction for this project is divided into segments as shown on the display here. The construction of the interchange at I-70 and Route 63 will begin in the summer of 2024 and will require multiple changes to traffic patterns. Construction of the I-70 and Route 54 interchange will begin in 2025 and can be constructed mostly offline to lessen the impacts to traffic.  Construction on the third lane of I-70 will begin in the summer of 2024 and two lanes of traffic along I-70 will be open in both directions during peak hours . Throughout construction, MoDOT will send out news releases and update social media channels regarding upcoming traffic impacts. Motorists are encouraged to sign up for these e-mails using the webform available on this webpage.

MoDOT has a formal noise wall policy it uses for every project that meets federal guidelines. The entire 20 miles for this project will be evaluated for noise walls. We expect to have the noise wall study for this project in early Fall after the design is finalized. More information about this topic will be communicated to the public at that time. 

Are there any plans to add pedestrian and bicycle facilities?

Yes. While the General Revenue funding for the Improve I-70 Program is to add a third lane eastbound and westbound Interstate 70 across the state between Blue Springs and Wentzville, the Columbia to Kingdom City section of the program has incorporated two previously funded MoDOT projects to also improve the I-70 interchanges at U.S. Route 63 (Columbia) and Route 54 (Kingdom City). With these interchange improvements, there are also several bicycle and pedestrian improvements at the I-70 and Route 63 interchange being included as well. These improvements are all new connections across I-70 and U.S. 63 that do not exist today. These additions include:

  • A sidewalk will be provided across the new Route 63 Connector bridge. This sidewalk will be on the west side of the bridge and will connect to the existing sidewalks at the intersection with Clark Lane on the north side of Interstate 70. After crossing Interstate 70 on the bridge, the sidewalk will continue south and connect to the existing sidewalks at the intersection of Business Loop 70 and Conley Road.
  • A sidewalk will be provided across the new St. Charles Road bridge. This sidewalk will be on the west side of the bridge and will connect to the existing sidewalks on both the north and south side of Interstate 70.
  • A sidewalk will be constructed along the Hannover Road Connection. This sidewalk will connect to the existing sidewalks near the intersection of Clark Lane and Hannover Road and continue south and go under Interstate 70 utilizing the new underpass. On the south side of Interstate 70, the new sidewalk will connect to the existing sidewalks at the intersection of I-70 Drive SE and Woodbridge Drive.
  • Although the sidewalk will not be constructed under this project, space is being left under the new Route 63 underpass for a future sidewalk. This underpass allows traffic from the large shopping center south of the connector to go under Route 63 and flow north to the connector. Since there are no existing sidewalks to connect to East of Route  63, the sidewalk will need to be constructed at a later date. 

Where can I learn more about the environmental process for this project?

This project has undergone extensive federal and state environmental reviews over the past 20 years. The project will have all if it’s necessary environmental permits and protective measures in place prior to construction starting in mid-July. The I-70 Environmental Impact Study can be found here: https://www.modot.org/improvei70/completed-studies.

Webform

Sign Up For Improve I-70 News.

Select which e-mail lists you'd like to join. For all Improve I-70 Program updates and monthly reports, select All Improve I-70 News. For project specific press releases, select the project you're interested in. Please note that you may not receive project specific press releases until the selected project begins procurement and/or construction.

*
Choose Your Subscription(s):

Improve I-70: Columbia to Kingdom City Milestones

Complete
EIS Re-evaluation
January 2022 - February 2024
milestone_icon
Complete
Industry Meeting
Thursday August 24th, 10:00am to 11:30am in Columbia, Missouri.

Watch the Recording

For industry access to information such as the sign in sheet and presentation from the industry meeting, please email improvei70@modot.mo.org and request access to Improve I-70: Columbia to Kingdom City's industry Sharepoint site.

 

milestone_icon
Complete
Public Information Meeting
Wednesday, Sept. 6, 5 to 7 p.m. – Battle High School Auxiliary Gym, located at 7575 St. Charles Rd., Columbia, MO.

MoDOT invited the public to attend informational meetings  to learn about the proposed plan and next steps for I-70. These were open house style meetings, and no formal presentations will be made. The public could attend the meetings anytime during the advertised hours, and the information will be the same at each location. MoDOT is currently in the planning stage of the Improve I-70 Program. MoDOT engineers shared preliminary information about the goals for improving I-70, possible construction schedules for the 200 miles, and next steps.  Learn more here.

milestone_icon
Complete
SOQ Due
October 2, 2023
milestone_icon
Complete
SOQ Shortlist
October 2023

The pre-qualified teams are as follows:

  • I-70 Constructors: Emery Sapp & Sons and Capital Paving and Construction – Joint Venture
    • Parsons
  • Millstone Weber.
    • Lunda and Jacobs

There are still opportunities for additional consultants and subcontracting firms to be added to each team.

milestone_icon
Complete
Issue RFP
October 2023
milestone_icon
Complete
Proposals Due
January 2024
milestone_icon
Complete
Commission Selection of Design-Build Team
February 14, 2024

Millstone Weber and designer Jacobs has been selected as the best-value proposer and Design-Build contractor for Improve I-70: Columbia to Kingdom City. This project was awarded at the February Missouri Highways and Transportation Commission meeting.

Press Kit

milestone_icon
Complete
Public Hearings
May 1 and May 2, 2024

Public hearings for Project #1 (Columbia to Kingdom City) were held in Columbia and Kingdom City where project plans, traffic control, and schedule were shared. 

  • Wednesday, May 1, 4 p.m. to 7 p.m. at Boone Electric Cooperative located at 1413 Rangeline St, Columbia, MO 65201.
  • Thursday, May 2, 4 p.m. to 7 p.m. at Kingdom City’s City Hall located at 5584 Dunn Dr, Kingdom City, MO 65262. 

The information shared at these meetings will the same at each location is available on the project website. Comments were accepted May 1 through May 23, 2024.

milestone_icon
Complete
Groundbreaking Ceremony
Thursday, June 13, 2024
milestone_icon
In Progress
Construction
Summer 2024 - Late 2027
milestone_icon
Image
Workers on an elevated platform

What is Design-Build?

Design-build is a delivery method that includes hiring one contracting team to complete the design work and build the highway improvement under one contract. MoDOT provides the project goals, budget and schedule and the contractor team completes the work. This technique has been known to significantly save time and provide cost savings.

Interactive Map

Embed
Improve I-70: Columbia to Kingdom City
Is Responsive
Embed Code
Image
I-70 at US 63

Need More Information?

We're here to help. For more information about Improve I-70: Columbia to Kingdom City, please contact a member of the Improve I-70 Central Project Team.