MoDOT Announces Prequalified Teams for Third Improve I-70 Project

Includes improvements to I-70 from Blue Springs to Odessa

JEFFERSON CITY – The Missouri Department of Transportation has received Statements of Qualifications (SOQs) from teams interested in competing for the contract to design and construct the third project of MoDOT’s statewide Improve I-70 Program. Improve I-70: Blue Springs to Odessa will add a third lane each direction on Interstate 70 from just west of MO Route 7 in Blue Springs to just east of Johnson Drive in Odessa. The project also includes interchange improvements at MO 131 in Odessa. 
 

Missouri’s FY2024 budget from the General Assembly signed into law by Gov. Mike Parson provides $2.8 billion in General Revenue for the costs to build a third lane of Interstate 70 across the state. The program will plan, design, construct, reconstruct, rehabilitate, and add three lanes in each direction on approximately 200 miles of I-70, from Blue Springs to Wentzville.

The pre-qualified teams are as follows:

  • Ames Construction
    • Ames Construction with designers Parsons Transportation Group
       
  • Capital - HDR
    • Capital Paving and Construction and Michels Road and Stone with designers HDR Engineering and TranSystems
       
  • Improve 70 Alliance
    • Emery Sapp & Sons and Clarkson Construction with designers HNTB and Bartlett and West
       
  • MasTec Design-Build Team
    • William Charles Construction Company, LLC and Koss Construction Company with designers T.Y. Lin International and Horner and Shifrin
       
  • Radmacher-Ideker Joint Venture
    • Radmacher Brothers Excavating Inc. and Ideker with designers Wilson and Company, Inc.

MoDOT will issue the Request for Proposals in January 2025 to these teams to work through development of their Design-Build proposals for the project. The department will work through the procurement process with these teams, who will submit their proposal for the potential selection of the winning contract in spring 2025. Construction could start as early as summer 2025. There are still opportunities for additional consultants and subcontracting firms to be added to each team.

Design-Build is a project delivery method that combines both the design and construction phases into one contract. The selected contract team completes the design and construction in parallel instead of in succession, which saves time and resources.

The project goals are as follows:

  • Deliver the project by December 31, 2028, within the program budget.
  • Provide an additional lane of travel in each direction on I-70 from Blue Springs to Odessa.
  • Modernize I-70 while improving the existing pavement, bridges, and interchanges to enhance safety and mobility.
  • Minimize construction impacts with a focus on work zone safety, communication, and construction staging while maintaining mobility.
  • Provide expanded employment opportunities while developing and using a diverse workforce.

For more information, call MoDOT at 888-ASK-MODOT (275-6636) or visit www.modot.org. To receive the latest statewide news and text alerts, signup for e-updates.

#ImproveI-70

Follow MoDOT: Facebook X (Twitter) | Instagram YouTube