ST. JOSEPH, Mo. – The Missouri Department of Transportation has contracted Vance Brothers, Inc. to complete a scrub seal project in Grundy, Mercer, Putnam and Sullivan counties. The project is scheduled to begin on Monday, April 20 on Putnam County Route E.
Traffic Impacts: During construction, the roadway will be narrowed to one lane with a pilot car guiding motorists through the work zone. Flaggers will also be present at intersections.
Tentative project schedule:
- April 20-27 – Putnam County Route E.
- April 27-28 – Sullivan County Route P.
- April 28-30 – Sullivan County Route E.
- April 29-May 5 – Grundy/Mercer County Route J.
- May 1-12 – Mercer County Route E.
- May 6 – Grundy County Route B.
- May 7 – Grundy County Route N.
Project schedule updates will be provided on the Traveler Information Map (http://traveler.modot.org/map/) and on the Planned Roadwork for Northwest Missouri press release sent out each Friday afternoon. The press release can be viewed by signing up for eUpdates at MoDOT E-Updates.
All work is weather permitting, and schedules are subject to change.
MoDOT asks drivers to work with us by always buckling up, keeping your phone down, slowing down and moving over in work zones. Know before you go and check what work zones you might encounter at traveler.modot.org.