PROJECT TIMELINE
Please review the project information and complete the comment form below by June 1.
Project Information
- Replace Greene County Route J box culvert over Turner Creek east of Springfield
- Replace Greene County Route J box culvert over Kinser Branch east of Springfield
- New roadway approaches will include 2-foot shoulders and improved sight distance
Traffic Impact
- Route J CLOSED at Turner Creek for up to 5 months
- Route J CLOSED at Kinser Branch for up to 3 months
- Culverts will not be closed simultaneously
- Access from Route J to Farm Road 150 will be temporarily restricted as crews work on the change of grade at the Turner Creek crossing
- Signed detour includes: Missouri Route 125 & U.S. Route 65
Culvert Facts
- Culvert over Turner Creek was built in 1935
- Culvert over Kinser Branch was built in 1900
- Route J carries 1,795 vehicles a day
Estimated Total Construction Cost: $2.6 million
Project Updates
-
Greene Co. Route J Culvert Replacement Project Focus of Virtual Public Meeting May 18-June 1
Springfield – Those interested in the Greene County Route J Culvert Replacement Project east of Springfield are invited to view the proposed improvements and project information via a virtual (online) public meeting from Monday, May 18, until Monday...
Frequently Asked Questions:
How will this work impact traffic on Route J?
Both culverts will be replaced one at a time and will require complete closures of Route J to remove the existing structures, build the new ones, and regrade the road to improve visibility, drainage, and driver comfort.
Will there be a signed detour?
A signed detour will redirect traffic approaching Route J on U.S. 60 and Route D/Sunshine St. to use U.S. 65 or Route 125 for northbound/southbound trips instead of Route J. The same detour will be used for closures at both locations.
Will I be able to access my property on Route J?
Yes. Complete closures of Route J will be localized to each culvert. Temporary access will be provided during construction to properties directly impacted by this work until completion of the project. Any occasional interruptions to access will be minimized and communicated to the affected property owners.
Does this project affect any local roads?
As a result of the proposed grade change at the Turner Creek crossing, access from Route J to Farm Road 150 will be temporarily restricted. Access to Spring Circle and Ridgeline Drive will not be interrupted, nor will access to Farm Roads 168 & 170 at the Kinser Branch crossing.
How long will construction be active at each location?
Work over Turner Creek is projected to last 131 days & work over Kinser Branch is projected to last 87 days.
Will MoDOT need to acquire additional right-of-way for this project?
Yes, additional right-of-way will be needed at both locations to construct the project. Please review the exhibits for additional information. A Right of Way representative will be contacting affected landowners to begin the acquisition process. For more information on the acquisition process, please see the Pathways of Progress display above.
The last day to leave comments on this project is June 1.
Project Contacts
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info
Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Ozarks Transportation Organization: Greene & Christian Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Kara Richart
Title
Transpiration Project Manager
Department
Design
Contact Info
Email: Kara.Richart@modot.mo.gov
Phone: (417) 408-4657
Email: Kara.Richart@modot.mo.gov
Phone: (417) 408-4657