Proposal Highlights

The selected Design-Build contractor team, Improve 70 Alliance, was one of three shortlisted Design-Build teams. The winning proposal highlights engineering and design endeavors set out before the teams and an understanding of the local, statewide, and national importance of an improved I-70. The winning proposal includes: 

  • Constructing a third lane in each direction on I-70 from Warrenton to I-64 in Wentzville, including replacing the existing I-70 lanes with new full-depth concrete pavement. 

  • Interchange improvements at I-70 and the I-64/Route 61 interchange. 

  • Interchange and outer road improvements in Foristell, Wright City, Warrenton, and at Route Z. 

  • Realignment at the railroad bridge on I-70 between Wentzville Parkway and Route Z. 

  • Addition of a third lane of travel to eastbound and westbound I-64 between I-70 and Route K. 

  • The team has also committed to keeping two lanes of travel open on I-70 in both directions during peak travel times.

Project Renderings

Proposed design renderings of Improve I-70 Warrenton to Wentzville. More renderings and information are avaliable on this webpage.