Counties Impacted
Greene
Route Impacted
413
Work Type
Bridge Replacement
Planning Phase

Project Milestones

Complete
Virtual Public Meeting
Monday, January 30 - Friday, February 10, 2023
milestone_icon
Public Meeting
4:30-6 p.m., Thursday, March 13
Location: Springfield-Greene County Botanical Center, 2400 S Scenic Ave, Springfield, MO 65807
(RESCHEDULED from February 20 due to winter weather road conditions)
milestone_icon
Construction
March 17, 2025
milestone_icon
Construction Completion
July 2025
milestone_icon

Project Facts:

  • Replace Missouri Route 413 (Sunshine Street) bridge over MNA Railroad in Springfield
  • Add/improve pedestrian facilities on both sides of roadway from Scenic Avenue to Marion Avenue

Construction: March 17, 2025

Estimated total project cost: $5,888,000

Completion Date: July 2025

Bridge Facts:

  • Bridge built in 1963
  • Bridge carries 26,164 vehicles a day
  • Old bridge 65 feet wide, 158 feet long

Traffic Impacts:

  • MO 413 (Sunshine St) CLOSED from east of Scenic Avenue to west of Marion Avenue for up to 4 months during construction
  • Detour: James River Freeway, Kansas Expressway, Chestnut Expressway, and US 160
  • All businesses will have access. Some access may be from Scenic Ave and not Sunshine Street during construction.
  • Westbound Kansas Exp. will have a single lane open to businesses with a traffic shift
  • Eastbound Sunshine will have a single-lane closure but will have access to north and southbound Scenic Ave