WESTBOUND U.S. ROUTE 54 WIDENING IN NORTH JEFFERSON CITY

Through the High Priority Unfunded Needs process, MoDOT identified improvements to the U.S. Route 54 corridor between U.S Route 63 and the Missouri River bridges. This includes expanding the westbound traveled way and reconfiguring the ramps for a safer and improved flow of traffic.

The extended right of way acquisition process has pushed the planned letting and contract award for the westbound expansion project to Fiscal Year 2026, subject to change.

Eastbound U.S. Route 54

In August 2023, the Missouri Highways and Transportation Commission approved separating the widening of U.S. Route 54 into two projects: eastbound and westbound. Learn about the eastbound expansion here: www.modot.org/us-route-54-eastbound-widening-callaway-and-cole.

PROJECT PROGRESS

In Progress
Planning, Design, and Right of Way Acquisition Phase

MoDOT and its contractor designed multiple options to address the needs of motorists travelling on U.S. Route 54 westbound between U.S Route 63 and the Missouri River bridge. Widening and improving the traveled way will require right of way acquisition.

milestone_icon
Complete
Public Input
Comment period: Dec. 28, 2022 – Jan. 20, 2023

Public Meeting

An open-house style public meeting was held Tuesday, Jan. 10, 2023, at the Jefferson City John. G. Christy Municipal Building. Attendees were able to view the design proposal options, ask questions of the project team, and submit comments. Comments were also able to be submitted online and by mail.

Meeting Exhibits

At the link below, find all exhibits presented at the in-person meeting. Comments were also accepted via an online form and by mail from Dec. 28, 2022, through Jan. 20, 2023.

milestone_icon
Complete
Eastbound/Westbound Divided into Separate Projects

The original design conceptions included improvements to both directions of travel on U.S. Route 54. After receiving comments, feedback and input from stakeholders and the community at-large, it was determined that additional right of way would be necessary to complete the westbound expansion.

However, the lengthy process to acquire necessary right of way requires additional time before MoDOT will be able to proceed with westbound decongestion efforts. On Aug. 1, 2023, the Missouri Highways and Transportation Commission approved making eastbound and westbound U.S. Route 54 separate projects.

Learn more about the eastbound improvements here: www.modot.org/us-route-54-eastbound-widening-callaway-and-cole.

milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is expected to be part of MoDOT's November 2025 letting when contractors submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their December 2025 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction is anticipated to begin in 2026. Proposed work would require lane shifts, temporary lane closures, and possibly some temporary narrowed lanes.

milestone_icon

Meeting Materials

Proposed Changes

Proposed changes presented at the January 2023 public meeting. A final design for the U.S. Route 54 westbound improvements has yet to be determined.

Project Updates

Frequently Asked Questions

Why is MoDOT expanding U.S. Route 54 in North Jefferson City?

With around 56,000 vehicles daily using U.S. Route 54 between Main Street and U.S. Route 63/Route 94 interchange, improvements are needed to create a safer, more efficient, and more reliable flow of traffic. The additional lane would help minimize congestion and improve traffic flow.

A lengthy right of way acquisition process extended the possible start date for construction on the westbound traveled way. With the eastbound right of way process complete and funding currently available, the Missouri Highways and Transportation Commission approved splitting each direction of U.S. Route 54 into its own project.