Project Summary
The Southwest District’s Kaysinger Basin Bridge Bundle will replace or rehabilitate up to 25 poor condition bridges in west central Missouri and bring them up to current standards. The majority of these bridges are on two-lane rural routes. These bridges connect and serve the communities and citizens of rural west central Missouri in Bates, Benton, Cedar, Henry, Hickory, St. Clair, and Vernon. On average, these bridges have been in place for 70 years.
Project Goals:
- Safely deliver the project within the programmed budget of $38 million.
- Maximize the number of locations to be addressed while providing quality, low maintenance structures and roadway approaches.
- Minimize impacts to the public through diligent construction efforts, flexibility in scheduling, and proactive communication.
- Deliver the project utilizing a diverse work force.
- Complete the project on or before November 15, 2027
REQUEST FOR QUALIFICATIONS DOCUMENTS
- Major Participant Information
- Reference Project Summary
- Resume Summary
- Receipt of Addenda
- Conflict of Interest
- Commitment of Key Personnel
- Debarment, Suspension, Ineligibility and Voluntary Exclusion Certificate
- Request for Qualifications Final
- Industry Meeting Sign-In
- Early Release Letter
- RFQ Addendum
- RFQ Letter
Project Milestones
You may e-mail your letter of interest to: kaysingerbridgebundle@modot.mo.gov
1-3 p.m., CDT, Benson Convention & Exposition Center
1008 E. Sedalia Ave., Clinton, MO 64735
Video recording of industry meeting available after August 1, 2024
10 a.m., CDT
The pre-qualified teams are as follows:
- Capital – Horner & Shifrin Team
- Capital Paving and Construction, Horner & Shifrin, EFK Moen, Geotechnology, Shafer & Hines
- ESS Team
- Emery Sapp & Sons, Bartlett & West
- Lunda Team
- Lunda Construction Company, Parsons Transportation Group, Terracon Consultants, HZ United
There are still opportunities for additional consultants and subcontracting firms to be added to each team.
4-6 p.m., Benson Convention & Exposition Center
1008 E. Sedalia Ave., Clinton, MO 64735
NEWS RELEASES
-
Bridge Improvement Project in Seven Counties Focus of Public Meeting Oct. 3
Clinton – The public is invited to participate in an in-person public meeting to learn more about plans to replace or rehabilitate up to 25 bridges in Bates, Benton, Cedar, Henry, Hickory, St. Clair, and Vernon counties, the Missouri Department of...
-
MISSOURI DEPARTMENT OF TRANSPORTATION NOTICE OF PUBLIC INFORMATION MEETING Kaysinger Basin Bridge Bundle Project; Project No. J7P3485
The Missouri Department of Transportation (MoDOT) will hold an open house public information meeting regarding the proposed improvements to the structures included in the Kaysinger Basin Bridge Bundle Design-Build Project throughout Bates, Benton...
-
Kaysinger Basin Bridge Bundle (KB3) Project Solicitation for Letters of Interest
The Missouri Department of Transportation (MoDOT) is soliciting Letters of Interest from companies interested in
providing Design-Build services for Southwest District’s Kaysinger Basin Bridge Bundle (KB3) Project.The project’s primary purpose is to...
Frequently Asked Questions:
How will you maintain traffic and access to my property or business during construction?
Bridges are expected to be closed while they are under construction, however access to adjacent properties will be maintained throughout that time. Some bridges in this project may be near other improvements on state-maintained highways. Should the need arise, the contractors will coordinate to minimize traffic conflicts and restrictions to properties.
Will construction interfere with emergency vehicle access?
Emergency vehicles will have access to all adjacent properties while each bridge location is under construction. Since the bridges will be closed and inaccessible while work is performed, the contractor will notify and coordinate with emergency services during the construction period.
Will traffic be detoured during construction of the project?
All bridges are expected to be closed while under construction. Of the 25 total bridges in the project, 15 have high enough traffic volumes to require signed detours.
When will construction begin?
Construction is anticipated to start in the summer of 2025. All construction activity is expected to be completed by November 15, 2027.
How long will construction last at each bridge?
After the construction project is awarded, a determination will be made on the amount of work to be done at each bridge. This will also determine the length of closure at each bridge. Once those determinations are made, the project’s web page will be updated. Currently, the project is anticipated to be awarded in early Spring 2025 and completed by November 2027.
How do I ask a question or leave feedback about this project?
MoDOT will be hosting a virtual (online) public meeting September 30-October 14. During that time you may return to this website and fill out a feedback form found here. You also may send us an e-mail at swcr@modot.mo.gov or call us at (417) 895-7600.